Civic Centre project update and cadetship opportunity

ccr web thumbnail.JPG

Work is currently underway on the old Lilydale Library building as part of Council’s Civic Centre redevelopment project.

Get the latest update from Luke Edwards, senior site manager for Johns Lyng Commercial Builders.

The first stage of the project has included:

  • locating, isolating and protecting existing service assets including sewerage and electrical
  • demolition works, in ground service excavation, laying and back filling
  • installing seismic steel to protect the building structure should an earthquake occur
  • installing two 25,000 litre underground rain water tanks
  • installing stormwater, rainwater, fire services and electrical conduits to the south and east side of the building.