Gasworks Lane Molong Update

Gasworks Lane 2.jpg

Crews have completed the new footpath and layback where Gasworks Lane exists on to the highway, opposite the Molong pool.

Crews are expected to finish up this week, returning on approximately the 27th of March to level the whole site with a GPS grader.

Concreting will then begin on new kerbs and footpaths after Easter.

Gasworks lane.jpg

Gasworks Lane 3.jpg

For more information about the Molong Town Centre Activation Plan click the link below.