Nyrang Creek Bridge Replacement

Nyrang Creek Bridge flood 271121-0207.JPG

Cabonne Council has awarded the design and construction tender for Nyrang Creek Bridge replacement.

The tender was awarded to Murray Construction Pty Ltd at the November 2023 Council meeting. The project was later endorsed by Transport for NSW (TfNSW) in late December 2023 as part of the approval process for the project commencement.

The reconstruction of Nyrang Creek Bridge located on Nangar Road has a project timeframe of approximately 6 months, with on-site works commencing mid-April 2024. Off-site works will be undertaken from week 1 to 13 of the program and includes the final detail design and pre-casting of the bridge components. On-site works include the reconstruction of the bridge, realignment of the approaching road pavement and decommissioning the temporary side access road once the new bridge has been reinstated.

The project has been funded by the NSW Government’s Essential Public Asset Reconstruction Works.