Poatina Power Station’s First Stage Upgrade Complete

Tasmanian Government

Nick Duigan, Minister for Energy and Renewables

Significant upgrades to Tasmania’s second largest hydro power station have been completed.
​
Minister for Energy and Renewables, Nick Duigan, said a major part of the upgrades has finished, including the first stage of recoating the inside of the Poatina penstock and 5.6km headrace tunnel.
​
“Poatina is a critical asset for the State, with the station generating around 10 per cent of Tasmania’s energy needs,” Minister Duigan said.
​
“The upgrade to the penstock, as well as major electrical upgrades and the refurbishment of a 60-year-old generating unit, will ensure reliability of the station for many more decades.
​
“New materials and technology will deliver more efficient power generation.”
​
In addition to the penstock upgrades and maintenance, Hydro Tasmania is also progressing a $200 million investment in upgrading all six of the station’s turbines.
​
Refurbishment of the second generating unit is expected to be completed in early 2027, with the second stage of the penstock recoating planned for mid-2027
​
“Our Government is continuing to build the infrastructure and deliver the services Tasmania must have as part of our 2030 Strong Plan for Tasmania’s Future,” Minister Duigan said.
​
“These important upgrades will help futureproof our electricity assets, delivering improved reliability with less maintenance required.
​
“Upgrading our power capabilities delivers on our commitment to grow our Northern economy outlined in the Northern Economic Plan.
​
“This work will ensure our valuable hydropower assets continue to deliver safe and clean energy for all Tasmanians for decades to come.”