Brick shortages: Changing approved wall construction on building permits

Due to brick supply constraints in WA, owners and builders may consider alternative wall types. This guidance helps builders, local governments and homeowners manage approvals and permit updates.

When this guidance applies

This approach is suitable when all of the following apply:

  • the only change is to the wall construction system (for example, cavity brick to brick veneer)
  • the owner agrees to the change rather than delaying the project until bricks are available. and
  • the change does not affect any planning approval or other local government requirements that apply to the property.

If the change goes beyond the wall system, or if you are unsure whether planning approval is affected (for example, because the outside appearance of the home will change), contact your local government before going ahead.

Why the change needs approval

A building permit approves a specific building design. Changing the wall system can affect whether the building still meets the applicable building standards. This includes but is not limited to structural adequacy, roof tie downs, energy efficiency, fire safety and termite management. A registered building surveyor needs to confirm that the new design complies.

At the end of the job, the builder must sign and lodge a notice of completion (BA7). This confirms the work was completed in relation to the building permit. If the walls were changed without approval, the builder cannot properly sign this notice. This can create legal and liability risks for the builder, the owner and others involved.

The Building Act 2011 does not set out a specific process for amending a building permit that has already been granted. As a result, local governments may record these changes in slightly different ways, depending on their processes and systems. The steps below set out an approach that should work in most cases.