Pump station to improve performance of Hallidays Point sewer network

MidCoast Council

Construction will begin early next month on a new sewage pump station at Hallidays Point.

The work is part of a $3.5 million project that will improve the operational efficiency of the Hallidays Point sewage scheme and allow for future growth and development in the area.

The new pump station will allow for sewage to be diverted from a number of nearby pump stations and transferred directly to the Hallidays Point Sewage Treatment Plant via a new rising main.

“This will reduce the volume of sewage the existing pump stations are required to process, giving our system more local capacity,” said Council’s Director of Infrastructure and Engineering Services, Rob Scott.

“As a result, we won’t need to upgrade these pump stations to keep up with future growth in the area and there’ll also be less chance of any sewage overflows occurring during wet weather events.”

Mr Scott said a permanent generator would also be installed at the new pump station to protect against power outages and an odour control system would be put in to ensure the community didn’t experience any unwanted odours.

While the work will take place close to Blackhead Road, there will be minimal disruption to traffic or the community.

The project is expected to be completed by March 2022, weather permitting.

/Public Release. View in full here.