Molong Town Centre Activation Update

MicrosoftTeams-image (1).jpg

MOLONG TOWN CENTRE ACTIVATION PROJECT AHEAD OF SCHEDULE!
Residents and visitors to Molong will notice that paving is currently underway on Stage 2, Phase 1 of the Molong Town Centre Activation Plan.
Stage 2, Phase 1 of the project is now due to be completed in early March 2024 (subject to weather).
Council has been able to accelerate the project due to favorable weather conditions and efficiency of local contractors.
The new trees are due to be on site within the next fortnight.
Council is continuing to review the project, and consider ways in which works can be expedited.
In the meantime, we want to continue to encourage all community members and visitors to support the Molong CBD businesses!

(PNG, 525KB)

/Public Release. View in full here.