Works toward a pre-Christmas opening remain on track
Works are continuing on West Dapto Road with Council committed to getting the road reopened before Christmas.
The recent weather conditions have been kind and allowed the works to continue to move forward with key milestones over the past two weeks including:
- The pavement stabilisation work has been completed, with most of the site ready for asphalt to be laid
- The concrete is being poured for new shared paths.
- Relocation of communications-related utilities completed
This means works to reopen the road are now 94 per cent complete.
“Each week we’re getting closer and closer to this phase of works being completed and the road reopened to traffic,” Lord Mayor of Wollongong Councillor Tania Brown said.
“It’s pleasing to see the table of works completed on Council’s website now have 8 of the 13 categories of work at 100 per cent.”
Over the next three weeks there will be additional work at night to keep the project moving forward. The work focuses on stormwater pit installation at the intersection of West Dapto Road and Rainbird Drive. The pits are the last part of the stormwater drainage network to be installed as part of road upgrades.
While Council is working to get the road reopened to traffic, the project will continue in early 2027 with a 40km/hr speed limit in place while it remains a construction zone. Some of the outstanding items will be landscaping, completion of the shared pathway links and other finishing works. Works will also continue in 2027 to upgrade the intersection of Shone Avenue and West Dapto Road.
“While Council has promised the community we will get this road reopened – and we’re committed to that – it will not mark the end of the project in its entirety,” Cr Brown said.
“Vehicles will be able to drive through, but it will remain a worksite with work continuing along this stretch of road.”
What the site will look like
When the road reopens there will be a 40km/h speed limit in force until all the remaining construction works have been finished. This speed zone will apply all day, every day, including when there are no workers on site. The 40km/h limit is not just for worker safety, it’s also to keep motorists safe from construction hazards. Once the works have finished, the road will be 50km/h.
There will be temporary line marking on the road until permanent line marking can be completed next year. What the line marking will look like is yet to be finalised, but it may be a mix of waterborne paint, “stick and stomp” markers, reflective cats’ eyes or line marking tape.
While the site fencing preventing people from driving on the road will be removed, there will be site fencing and barriers at various locations on either side of the road to support the construction crews’ safety when they return to the site in January.
The shared path will not be open prior to Christmas as adjacent construction works will continue in 2027.

Image: A typical klemmfix barrier setup delineating the road from adjacent construction works. Water barriers and concrete barriers may also be used where appropriate.
Pavement verses spray seal
A road is constructed from multiple layers of materials which, once completed, form a smooth surface.
The asphaltic concrete is the last layer that is installed to complete a road and is the black, smooth finished surface. It is laid on top of a spray seal layer. The spray seal layer creates a waterproof surface that protects the road’s foundational layers.
We are optimistic that, with the right weather, we will have sections of the West Dapto Road worksite asphalted in December.
However, while we’re working to have as much of the site asphalted as possible, this is the last layer of the road to be constructed. We need the works on the sections to be completed, and the right weather conditions to complete asphalt installation.
There are 3 discrete areas including either side of Lovelocks Bridge and at the intersection of West Dapto Road and Rainbird Drive, where we will be working right up to our deadline to get the construction completed to a point where the road is safe to reopen.

Image: recently installed spray seal on a section of West Dapto Road with a final asphalt layer to still be installed on top.

Image: asphalt placed on West Dapto Road in the first stage of works completed in 2023.
What are some of the outstanding works?
While a large proportion of the concrete shared pathways will be completed, the pedestrian bridge around one of the culverts is yet to be completed. We’ve amended plans to manage the impact of delays associated with the site’s resident microbats, including the introduction of this bridge.
There are two Sydney Water pits that are due for replacement within the road carriageway. These must be completed before the roadworks can be finished. If this isn’t done prior to Christmas, we will carry out temporary work such as a road plate with an asphalt ramp to allow drivers to use the road.
A large and deep stormwater pit located near Rainbird Drive is under construction. There are challenging site conditions that the crew is navigating to complete the works. Should the pit not be ready to support vehicle loads prior to the open day, there may be a temporary diversion around the pit on the road shoulder to make sure that two-way access is provided.

Image: one of two subsurface Sydney Water pits (lower left-hand corner) that need to be adjusted to the new finished surface level.

Image: the newly installed pedestrian bridge adjacent Lovelocks Bridge (fibre reinforced polymer decking and handrails still to be installed).
What will happen in early 2027?
The crews will return to the site no later than mid-January 2027. Some of the key pieces of work that’ll be completed along this section of West Dapto Road include:
- Landscaping along the road corridor
- Any outstanding shared path links
- Permanent line marking
- Signage and other road furniture installation
- Minor shaping of the road embankment, spreading of topsoil and grass seeding and turf
- Other miscellaneous tasks to complete upgrades
- Upgrades to the Shone Avenue intersection. Whilst we have recently obtained approval for a revised design from Sydney Water, temporary barriers will be in place as part of intersection upgrades.

Image: the current temporary arrangement with water barriers at Shone Avenue.
A detailed breakdown of further works completed to date is available at Council’s West Dapto Road project page , which will continue to be updated fortnightly. Community members can also sign up for regular project updates via our engagement page .
The West Dapto Road upgrade project is proudly funded by the NSW Government in association with Wollongong City Council.