Miles | Warrego Highway | Dogwood Creek Bridge | Change of access

National Road Transport Association

From 1 December 2022 the following mass restrictions for Class 1 OSOM platforms will apply over Dogwood Creek Bridge (west side of Miles), due to structural capacity limitations.

Class 1 OSOM platform combinations:

  • must travel on the centreline of the bridge at safe operating speed (typically 30-40km/hour)
  • must be escorted by a minimum of
    • One Level 2 Escort OR one QPS Escort in front of the combination to hold oncoming vehicles
    • One Level 1 Pilot at the rear of the combination to ensure no other heavy vehicles are within 50m of the load as it crosses the structure
  • additional pilot/escorts as required for general travel on the permit must be complied with
  • unloaded platforms may travel in lane when safe to do so.

New applications for Class 1 OSOM loaded platforms with 8 or more axles must include a completed F4846 Load Mass Declaration form, including the following additional information:

  • the registration numbers of all modules making up the platform
  • calculation of the total Tare Mass of the platform
  • the total loaded platform mass (includes mass of indivisible load plus Tare Mass of platform).

This information will provide TMR with a better understanding of the actual loading the structure is being subjected to, and will assist with the monitoring and overall management of the structure.

Loads NOT PERMITTED over Dogwood Creek Bridge

Platforms for which the Gross Mass exceeds the limits in the following table are not permitted to travel over Dogwood Creek bridge:

Note: up to 28t on a tandem dolly is also permitted with the platform

TMR is working with industry and Local Government to identify a pre-approved detour. Details of the detour and how to re-route existing permits will be provided in due course.

/Public Release. View in full here.