Durham Road Construction Update – For Week 8th April


Durham Road Construction Works Notice

As part of our commitment to improving the infrastructure in our community, we’d like to inform you of the work scheduled to take place for the week of April 8 to April 12.
Here’s what to expect:

Monday 8th April: Milling and removal of kerb.

Tuesday 9th April: Removal of kerb and lowering of services.

Wednesday 10th April: Foundation pavement works.

Thursday 11th April: Foundation pavement works.

Friday 12th April: Foundation pavement works and installation of subsoil drainage.

These activities will affect access to residents’ properties. The Contractor will be in direct communication with affected residents throughout this period. If you have concerns regarding driveway access, please reach out to Council and request to speak with the project manager.
Please note that these construction activities are extremely sensitive to weather conditions, especially wet weather, which may affect the contractor’s ability to carry out certain tasks.
Looking ahead to the week of April 15th to April 19th, the construction program includes the continuation of foundation pavement establishment, installation of subsoil drainage, and commencement of subbase material importation.
Thank you again for your cooperation and patience as we continue to carry out these essential works.
/Public Release. View in full here.